Mobilisation

Our Mobilisation programme describes the bringing together of the new REC code manager service partners and the journey towards launching the new REC Code Manager Service from 1st September 2021.

What is it?

The programme is divided into three critical path milestones, M1, M2 and M3.  

Milestones M1 and M2 were delivered to time on the 18th December 2020 and 9th April 2021 respectively. Milestone M3 is tracking to plan for delivery on 30th July 2021

During the Milestone M3, April to July timeline, the REC Code Manager is completing the build and test of the service areas required to support the REC Code Manager enduring service. This includes all the technologies, business processes, user guides and operational readiness activities to be ready for 1st September. Rigorous testing will be conducted including UAT with industry parties.  

For more details on the REC Code Manager visit their page here.